How to get take offs in my reports. say I have 2700' linear feet of 2 x 4 studs how do I get told how many 8 ' studs I need?
or bricks or block from sqf , I know how to do it myself but I wanted cost and take off in my report
Did I buy the wrong ext ?.
-
Hi James - I would suggest creating a 'studs' layer / tag and putting all of your 2x4 studs on that layer. Then, use the appropriate factor to convert from linear feet to studs. That way, when you export a 'cost detail report' you will see the total number of 8 ft studs needed. You can use the same approach for brick or block.